+- 24/7/02 - [**Master**](/notes/house/bath) drywall
|
|
|
|
+- 25/6/30-7/1 - [**Master**](/notes/house/bath) electrical
|
|
|
|
+- 25/6/17-20 - [**Master**](/notes/house/bath) plumbing
|
|
|
|
+- 25/6/02 - [**Master**](/notes/house/bath) Demo ( 4.5 days 2,3,4,10,11 )
|
|
|
|
+- 25/4/16 - **Gas** lines installed
|
|
|
|
+- 25/4/10 - **Roof** replaced - 7am -> 6pm - finished
|
|
|
|
+- 25/4/02 - **windows** replaced (+ sunroom/office)
|
|
|
|
+- 25/3/26 - CPW marked utility lines for gas
|
|
|
|
+- 25/3/36 - [studio](/notes/house/studio.md) cabinets installed
|
|
|
|
+- 25/3/25-26 - Ferqueron & Sons - remove two side pines and rear leaning oak ๐ณ
|
|
|
|
+ - grind two stumps and keep woodchips as mulch
|
|
|
|
+- 25/3/25 - WCTel on site to reroute fiber optic line
|
|
|
|
+- 25/3/19 - Mountz glass to measure rear, office, and sun room windows
|
|
|
|
+- 25/3/18 - GC meeting ( painter, carpet, doors, plumbing, tankless, gas line )
|
|
|
|
+- 25/3/10-19 - Framing crew - trusses installed / siding repaired
|
|
- 25/03/13 - [trusses installed](/notes/house/helene)
|
|
- 25/03/13 - [trusses installed](/notes/house/helene)
|
|
- 25/03/05 - second [insurance adjuster](/notes/house/helene-ins-adjust.md) met with general contractor
|
|
- 25/03/05 - second [insurance adjuster](/notes/house/helene-ins-adjust.md) met with general contractor
|
|
- 24/12/10 - added Helene [Insurance Claim](/notes/house/helene-ins-adjust.md)
|
|
- 24/12/10 - added Helene [Insurance Claim](/notes/house/helene-ins-adjust.md)
|