@@ -16,6 +16,8 @@ We've had some hiccups along the way, so I just wanted to start list of issues w
|
|
- Communication lackluster
|
|
- Communication lackluster
|
|
- quotes and invoicing incomplete
|
|
- quotes and invoicing incomplete
|
|
- requested payment before work was completed
|
|
- requested payment before work was completed
|
|
|
|
+ - Inconsistent notice of subcontractors arriving onsite
|
|
|
|
+ - sometimes no notice and sometimes just 15 minute notice
|
|
- Timeliness
|
|
- Timeliness
|
|
- slow pace - some contractors will work for just a couple of hours a day for a week.
|
|
- slow pace - some contractors will work for just a couple of hours a day for a week.
|
|
- Broken Sewer Line
|
|
- Broken Sewer Line
|
|
@@ -26,18 +28,23 @@ We've had some hiccups along the way, so I just wanted to start list of issues w
|
|
- contractor puked in the yard because he came hungover
|
|
- contractor puked in the yard because he came hungover
|
|
- left food trash in buckets upstairs that caused a bug infestation
|
|
- left food trash in buckets upstairs that caused a bug infestation
|
|
- had to drive over to GA to confirm quartz because couldn't get what was promised
|
|
- had to drive over to GA to confirm quartz because couldn't get what was promised
|
|
--
|
|
|
|
|
|
+- didn't communicate the schluter was horizontal and not vertical
|
|
|
|
+- didn't fix cut drywall in downstairs bathroom for quite some time
|
|
|
|
+ - left it open and we taped the piece back into it
|
|
|
|
+
|
|
|
|
|
|
**Craftsmanship**
|
|
**Craftsmanship**
|
|
|
|
|
|
|
|
+- messed up the hot water install so we didn't have cold water for a day
|
|
|
|
+- poured water under the house instead of piping it out
|
|
- left a pile of debris in the yard for three months
|
|
- left a pile of debris in the yard for three months
|
|
-- left the old sliding door in the yard for two months
|
|
|
|
|
|
+- left the old sliding door in the yard for a month
|
|
- we personally hauled off several loads of trash
|
|
- we personally hauled off several loads of trash
|
|
- drywall not consistent or square in spots
|
|
- drywall not consistent or square in spots
|
|
- dropping drywall at hvac intake
|
|
- dropping drywall at hvac intake
|
|
- not square where the corners meet
|
|
- not square where the corners meet
|
|
- didn't use the waterproof type throughout the bathroom
|
|
- didn't use the waterproof type throughout the bathroom
|
|
- - make patches where it should have been an entire board replaced
|
|
|
|
|
|
+ - made patches where it should have been an entire board replaced
|
|
- ripped out a closet that didn't need to be removed
|
|
- ripped out a closet that didn't need to be removed
|
|
- threw away good materials and unnecessary demo
|
|
- threw away good materials and unnecessary demo
|
|
- duct vents, bi-fold doors
|
|
- duct vents, bi-fold doors
|
|
@@ -50,9 +57,11 @@ We've had some hiccups along the way, so I just wanted to start list of issues w
|
|
- trash in yard
|
|
- trash in yard
|
|
- broken hardware on bifold doors
|
|
- broken hardware on bifold doors
|
|
- paint on tile floor
|
|
- paint on tile floor
|
|
|
|
+- had to repaint and drywall because of poor work
|
|
|
|
+- didn't install backing support for grab bar
|
|
|
|
|
|
**Costs**
|
|
**Costs**
|
|
|
|
|
|
- Requested payment before work was completed
|
|
- Requested payment before work was completed
|
|
- saying that y'all 'had a lot of money' out there
|
|
- saying that y'all 'had a lot of money' out there
|
|
-- promissed to charge costs on materials
|
|
|
|
|
|
+- promised to charge costs on materials
|