+title: Renovation Costs
|
|
|
|
|
+image: https://davidawindham.com/wha/helene-1.jpg
|
|
|
|
|
+hide_table_of_contents: true
|
|
|
|
|
+---
|
|
|
|
|
+
|
|
|
|
|
+:::warning[Private Page]
|
|
|
|
|
+
|
|
|
|
|
+:::
|
|
|
|
|
+
|
|
|
|
|
+
|
|
|
|
|
+
|
|
|
|
|
+These are the cost related to the hurrican helene [repairs](/notes/house/helene) and post helene renovations on the [studio](/notes/house/studio), master, and [bath](/notes/house/bath). Here are links to the .pdfs for the original [Estimates](/pdf/KLTimmerman-Estimates.pdf) and [Invoices](/pdf/KLTimmerman-Invoices.pdf). I'm using this page to share some questions and comments with the contractor and the boss. We've also started a document for the remaining quality control [issues](/notes/house/kl-timmerman-issues).
|
|
|
|
|
+
|
|
|
|
|
+## KL Timmerman Enterprises, LLC
|
|
|
|
|
+
|
|
|
|
|
+### Invoice(s) # 35435 / # 35457 / # 35663 / # 35701
|
|
|
|
|
+
|
|
|
|
|
+||Downstairs Office - Invoice # 35435|||
|
|
|
|
|
+|---|---|---|---|
|
|
|
|
|
+|1. Fabricate and install lower cabinets with pull out shelving for printer.||||
|
|
|
|
|
+||- The center will be desk area.|||
|
|
|
|
|
+||- Fabricate bookcases to set on top of the counter top.|||
|
|
|
|
|
+||* Height to be about 29 1/4". With counter top the overall height will be around 30".|||
|
|
|
|
|
+||* Alder wood will be used.|||
|
|
|
|
|
+||Labor and materials |$8,200.00||
|
|
|
|
|
+|2. Install smooth black Formica countertop the width of the room.||||
|
|
|
|
|
+||* The counter top will have 1 seam due to the length.|||
|
|
|
|
|
+||Labor and materials |$1,000.00||
|
|
|
|
|
+|3. Install an outlet for the printer.||||
|
|
|
|
|
+||- Install 1 quad outlet.|||
|
|
|
|
|
+||- Install TV outlet.|||
|
|
|
|
|
+||* Use existing circuit.|||
|
|
|
|
|
+||Labor and materials |$937.00|๐๐ป an outlet?|
|
|
|
|
|
+|||||
|
|
|
|
|
+||<b>TOTAL</b>|<b>$10,137.00</b>||
|
|
|
|
|
+|||||
|
|
|
|
|
+
|
|
|
|
|
+<div><br/><br/></div>
|
|
|
|
|
+
|
|
|
|
|
+||Roof / Siding - Invoice # 35457|||
|
|
|
|
|
+|---|---|---|---|
|
|
|
|
|
+|1. Roof trusses. ||$1,983.80||
|
|
|
|
|
+|2. Remove existing roof shingles, roof sheeting, overhang soffit, and trim in area of repair at upper bedroom of home.||$17,339.83||
|
|
|
|
|
+||- Remove four damaged 2x4 trusses.|||
|
|
|
|
|
+||- Replace damaged trusses.|||
|
|
|
|
|
+||- Install new 1/2" OSB plywood using clips in area of repair only.|||
|
|
|
|
|
+||- Remove existing 1/2" rough sawn plywood siding with 1x8 cedar trim boards at rear wall of bedroom including damaged area on side wall.|||
|
|
|
|
|
+||- Install new brick mould trim to one window unit at rear of bedroom wall.|||
|
|
|
|
|
+||- Install new siding and soffit trim to area of repair as to match existing as close as possible.|||
|
|
|
|
|
+|3. Remove existing shingles and haul away all job related debris. ||$20,522.04||
|
|
|
|
|
+||- Install Atlas 35 year architectural shingles to entire roof system.|||
|
|
|
|
|
+||- Install synthetic underlayment barrier to entire roof system.|||
|
|
|
|
|
+||- Install shingle over ridge vent to gable ridge of home.|||
|
|
|
|
|
+||- Replace all vent pipe collar boots and install new flashing at any chimneys's.|||
|
|
|
|
|
+|4. Hang sheetrock on ceiling at upstairs bedroom and repair closet ceiling and wall.||||
|
|
|
|
|
+||- Apply texture at repair area.|||
|
|
|
|
|
+|5. Caulk, prime, and putty one new side and touch up handrails.||||
|
|
|
|
|
+||- Caulk, prime, and putty soffit on both sides and siding as needed.|||
|
|
|
|
|
+||- Paint inside bedroom, bath, and closet ceiling, trim, and walls. Exterior $4860.00 - Interior $3071.25|||
|
|
|
|
|
+|6. Install approximately 114 lf og Alcoa 6" seamless aluminum guttering to the home.||||
|
|
|
|
|
+||- Install approximately 75lf of commercial 3 x 4 downspout to gutter system.|||
|
|
|
|
|
+|7. Install Sureflow 6" leaf protection to new guttering on the home.||||
|
|
|
|
|
+|8. Rental fee for telehandler to set roof truss and make exterior repairs. ||$3,111.45||
|
|
|
|
|
+|9. Furnished and installed two 5/8" clear tempered IG units. ||$1,136.00|๐๐ปโ๏ธ duplicated on addendum|
|
|
|
|
|
+|10. Remove existing sliding patio door unit from rear upper level of home.||||
|
|
|
|
|
+||- Haul away job related debris.|||
|
|
|
|
|
+||- Install one Weathershield Signature Series sliding patio door unit with painted aluminum clad trim.|||
|
|
|
|
|
+||- Interior of door unit will be unfinished wood.|||
|
|
|
|
|
+||- Door unit will come with Low-E performance glass units.|||
|
|
|
|
|
+||- Door unit will have a standard 2 point lock system with keyed lock.|||
|
|
|
|
|
+|11. Replace interior and window and door casing.||||
|
|
|
|
|
+|12. Cut out ceiling in the bedroom to assess damage and hauled off debris. ||$540.11||
|
|
|
|
|
+|13. Install padding and carpet.||||
|
|
|
|
|
+|14. Blown-in insulation in master bedroom ceiling.||||
|
|
|
|
|
+|15. Duct work repair/replacement. * TO BE FORTHCOING||||
|
|
|
|
|
+|16. Install ceiling fan in the master bedroom - labor only||||
|
|
|
|
|
+||- Remove and reset the exterior light fixture by the sliding glass patio door.|||
|
|
|
|
|
+|||||
|
|
|
|
|
+||TOTAL|$44,633.23|โ
|
|
|
|
|
|
+|||||
|
|
|
|
|
+
|
|
|
|
|
+<div><br/><br/></div>
|
|
|
|
|
+
|
|
|
|
|
+||Master Suite Remodel - Invoice # 35663|||
|
|
|
|
|
+|---|---|---|---|
|
|
|
|
|
+|DEMO AND ROUGH-IN CARPENTRY||||
|
|
|
|
|
+|1. Demo walls associated with remodel.||||
|
|
|
|
|
+||- Remove both shower units, vanities/tops, and plumbing fixtures.||
|
|
|
|
|
+||- Take up existing floor tile and subfloor to access plumbing.|||
|
|
|
|
|
+||Labor - range between $5000.00 - $6500.00|$5,239.44||
|
|
|
|
|
+||Disposal fee at landfill allowance |$0.00||
|
|
|
|
|
+|2. Cut and install new subfloor.|Labor |$1,363.00||
|
|
|
|
|
+||Materials |$416.60||
|
|
|
|
|
+|3. Frame new walls, install supports in shower, frame custom niche in shower.|Labor|$1,785.00||
|
|
|
|
|
+||Materials|$381.94||
|
|
|
|
|
+|PLUMBING||||
|
|
|
|
|
+|1. Cap lines for demo.|- Re-route water (will use Pex pipe) and drain lines for plumbing fixture locations.|||
|
|
|
|
|
+||- Re-route vent through the roof.|||
|
|
|
|
|
+||Labor and plumbing materials |$5,625.00||
|
|
|
|
|
+|2. Install new plumbing valves and fixtures.|Labor|$3750.00||
|
|
|
|
|
+|3. Install a gas tankless water heater| Labor, water heater, and plumbing materials|$3750.00||
|
|
|
|
|
+|Fixtures||||
|
|
|
|
|
+|1. Quarles quote||$3607.29||
|
|
|
|
|
+|2. Toilet from Quarles||$306.79||
|
|
|
|
|
+|3. Moen rough-in valve for shower ||$194.41||
|
|
|
|
|
+|4. Toilet - American Standard Aspirations 252AA899.020 * with tax ||$1,781.55|๐๐ป $450 from Home Depot?|
|
|
|
|
|
+|ELECTRICAL||||
|
|
|
|
|
+|Bathroom 1. Demo existing as needed.|- Install customer provided heater/fan combo outside shower area and switched on door wall opposite of shower.|||
|
|
|
|
|
+||- Install an outlet on the bathroom entry door wall opposite of shower.|||
|
|
|
|
|
+||- Install 3 wafer lights on a dimmer switch - 3 way - switch to be located on bathroom entry door wall opposite of shower and on the left end wall of vanity. * Only installed 2 wafers, added 2 retrofit can trims for stairwell.|
|
|
|
|
|
+||- Install 2 vanity lights - switch to be located on left end wall of vanity.|||
|
|
|
|
|
+||- Install 2 GFI's - to be located on left and right walls of vanity.|||
|
|
|
|
|
+|Master bedroom ||||
|
|
|
|
|
+|1. Install new ceiling fan - switch to be located on left wall entering the bedroom.|- Switch the 2 existing outlets on long wall of bedroom for lamps - switch to be located of left wall entering the bedroom.|||
|
|
|
|
|
+||Labor and materials |$5,225.00|๐๐ป|
|
|
|
|
|
+||Panasonic Whisper Coy heater/van 811A * Customer provided|||
|
|
|
|
|
+||2 vanity lights |$503.05||
|
|
|
|
|
+||CREDIT FOR INSTALLATION OF CEILING FAN FROM INSURANCE. |-$250.00||
|
|
|
|
|
+|DRYWALL|||
|
|
|
|
|
+||1. Make repairs to drywall from demo.|||
|
|
|
|
|
+||2. Install drywall on walls and ceiling associated with master bathroom and bedroom remodel.|||
|
|
|
|
|
+||Labor and materials |$4,620.00||
|
|
|
|
|
+|TRIM AND DOORS ||||
|
|
|
|
|
+|1. Install baseboard in the bedroom, bathroom, hallway, and Ginny's closet - all associated with remodel.|- Install bi-hinge bedroom doors and casing - 6 panel raised solid core. INSTALLED BIFOLD|||
|
|
|
|
|
+||- Install bi-hinge closet doors and casing - 6 panel raised solid core. INSTALLED BI-FOLD|||
|
|
|
|
|
+||- Install 2 door units for bathroom and casing - 6 panel raised solid core. DID NOT DO|||
|
|
|
|
|
+||Labor |$2,200.00||
|
|
|
|
|
+||Trim |$453.65||
|
|
|
|
|
+||Allowance - Door units, bi-hinge doors, hinges, ball catches, and door handles. |$983.75||
|
|
|
|
|
+||* Door allowance etc was 1200.00. Actual cost was 1585.91. Giving credit for the 2 bathroom doors 361.66. Giving credit for 1/2 of the bi-fold closet door - agreed on bi-hinge and we threw away the existing bi-fold - bought new bi-fold doors at 481.00 - will split this and gave credit for 240.50|||
|
|
|
|
|
+|PAINTING||||
|
|
|
|
|
+|1. Paint all ceilings, walls, and trim associated with master bedroom and bathroom remodel.|Labor and materials|$3,125.00||
|
|
|
|
|
+||-Stairwell long wall, short wall at end of landing, trim, and the ceiling - $1,312.50|||
|
|
|
|
|
+||- One wall, trim, and door in Ginny's closet - $593.75 * No extra charge for painting complete closet.|||
|
|
|
|
|
+||- Bathroom walls, ceiling, trim, and door - $1,218.75|||
|
|
|
|
|
+|MISCELLANEOUS||||
|
|
|
|
|
+|1. Shower and bathroom floor tile|Labor |$5,625.00||
|
|
|
|
|
+||Tile allowance for shower walls, shower floor, and outside floor * Tile cost for shower and outside floor was 3660.58|$3,660.58||
|
|
|
|
|
+||Freight allowance |$300.00||
|
|
|
|
|
+||Materials - grout, caulk, schluter, backerboard, schluter Kerdi shower tray, etc. This is included in the 3660.58 amount|||
|
|
|
|
|
+|2. Bedroom padding and carpet|Labor|$1,050.00||
|
|
|
|
|
+||- Carpet allowance and pad together was 4291.24 |$4,291.24||
|
|
|
|
|
+||#10 pad and seam tape|||
|
|
|
|
|
+||CREDIT FROM INSURANCE ON 216 s ft ALLOWANCE FOR INSURANCE.|-$1391.04||
|
|
|
|
|
+|3. Vanity|- Custom build and install vanity.|||
|
|
|
|
|
+||Allowance |$8800.00||
|
|
|
|
|
+||Allowance for knobs/pulls|||
|
|
|
|
|
+|4. Vanity top and sinks|- Template and install|||
|
|
|
|
|
+||Allowance for top and sinks Actual cost |$3,833.40||
|
|
|
|
|
+|5. Shower door TO BE ON FINAL DRAW|- Custom shower door and installation allowance. |$3000.00||
|
|
|
|
|
+|6. Mirror - remove existing mirror and reinstall.||$250.00|๐๐ปโ๏ธ duplicate|
|
|
|
|
|
+|7. Install bathroom accessories|Grab bar 50.00 each * WILL BE ON FINAL INOICE|$0.00||
|
|
|
|
|
+||Towel bars, robe hooks, toilet paper holder, and 2 hand towel rings.|$125.00||
|
|
|
|
|
+||Allowance on accessories * Cost of accessories including closet pulls |$388.64||
|
|
|
|
|
+|8. Allowance on custom linen closet. ||$2,500.00||
|
|
|
|
|
+|EXTRAS - ALL AT COST||||
|
|
|
|
|
+||Permit fee paid |$110.00||
|
|
|
|
|
+||Extra insulation |$800.00||
|
|
|
|
|
+||Extra quad outlets and light and switch in the crawlspace|$645.00||
|
|
|
|
|
+||Closet labor |$1550.00||
|
|
|
|
|
+||Closet materials |$739.80||
|
|
|
|
|
+||Painting closet and drawer fronts |$680.00||
|
|
|
|
|
+||Installed outside light fixture |$80.00||
|
|
|
|
|
+||Installed uarter round in carpeted rooms|$200.00||
|
|
|
|
|
+||Quarter round|$61.63||
|
|
|
|
|
+|9. Hung sheetrock on ceiling at upstairs bedroom and repaired closet ceiling and wall. |- Applied texture at repair area.|$2835.00|๐๐ป|
|
|
|
|
|
+|10. Caulked, primed, and puttied one new side and touched up handrails.||$7331.25|๐๐ปโ๏ธ|
|
|
|
|
|
+|11. Blown in insulation in master bedroom ceiling. |* This was considerably less.|$480.00||
|
|
|
|
|
+|||||
|
|
|
|
|
+||<b>TOTAL</b>|<b>$93,006.97</b>||
|
|
|
|
|
+|||||
|
|
|
|
|
+
|
|
|
|
|
+<div><br/><br/></div>
|
|
|
|
|
+
|
|
|
|
|
+||Addendum - Invoice # 35701|||
|
|
|
|
|
+|---|---|---|---|
|
|
|
|
|
+|Extra Items Requested||||
|
|
|
|
|
+|1. Installed 2 chimney caps and a custom fabricated border shade. ||$874.70||
|
|
|
|
|
+|2. Replaced gutters around remainder of home. ||$2,978.08||
|
|
|
|
|
+|3. Installed leaf protection. ||$1794.90||
|
|
|
|
|
+|4. Master bedroom - replaced 2 clear IG units. ||$1,336.00|๐๐ปโ๏ธ duplicate|
|
|
|
|
|
+|||||
|
|
|
|
|
+|REGARDING INVOICE #35663||||
|
|
|
|
|
+|1. Page 4 - Item # 5 - Shower door was invoiced at $3000.00 - Actual cost was $2918.00|- Labor and materials to install custom door. |-$82.00||
|
|
|
|
|
+|2. Page 4 - Item #6 - Mirror - *|- cut existing mirror and installed |$190.00|๐๐ปโ๏ธ duplicate|
|
|
|
|
|
+|3. Page 5 - Item #7 - install bathroom accessories|- Installed grab bar |$50.00||
|
|
|
|
|
+|||||
|
|
|
|
|
+|Remaining items from the Insurance estimate that have not been invoiced.||||
|
|
|
|
|
+|1. Removed existing sliding patio door unit from rear upper level.|- Installed Weathersheild unit.|||
|
|
|
|
|
+||Labor |$3,347.50||
|
|
|
|
|
+||Door unit |$3,914.62||
|
|
|
|
|
+|||||
|
|
|
|
|
+|2. Installed 114 lf of Alcoa 6" seamless gutter.||||
|
|
|
|
|
+||Labor and materials |$2,689.60||
|
|
|
|
|
+|3. Install Sureflow 6" leaf protection.||||
|
|
|
|
|
+||Labor and materials |$1,635.55||
|
|
|
|
|
+|4. Repaired/replace duct wor and connected at drops.||||
|
|
|
|
|
+||Labor and materials |$1,050.00||
|
|
|
|
|
+|||||
|
|
|
|
|
+||<b>TOTAL</b>|<b>$19,778.95</b>||
|
|
|
|
|
+|||||
|
|
|
|
|
+|||||
|
|
|
|
|
+||<b>GRAND TOTAL</b>|<b>$167,556.15</b>||
|