--- title: Issues image: https://davidawindham.com/wha/helene-1.jpg draft: true --- # Issues We've had some hiccups along the way, so I just wanted to start list of issues we've had with the general contractor and sub contractors so they're not forgotten when we need to reference them. ## Punch List **Exterior** - rear upper deck & railings - deck light - caps on doubled 2x12s - was told they would be caulked to look like 4x12s - insulation and pipes in crawlspace - proper drainage pipes on hot water heater - chimney seal, cap, & wrap - gutters left metal intact from previous gutters - leaving visable gaps under the shingles that are large enough that small critters could enter the attic. - missing downspouts on gutters - hole in gutter to right of entrance - water dripping along wood under upper gutter. - leaking downspout connector entrance - painting in spots - front doors - were measured but not follow up **Interior** - missing closet lights - hvac ductwork - damaged sliding doors - broken hardware on bifold doors - door hardware for bedroom - missing foot boards and crown molding - crooked wall in bedroom corner - lots of bad drywall work - tape marks in ceiling - sliding door not caulked - broken shower wand tube - downstairs ceiling repair from two separate leaks and jackhammer cracking - downstairs bathroom paint - bathtub not properly installed - slides around - no backsplash or water proofing on the wall of bathtub - white caulk on bathtub faucet - paint on tile floor - cracked floor trim from carpet puller ## Management - Timeliness - slow pace - some contractors will work for just a couple of hours a day for a week. - took **over a year** to complete the project - General contractor has only been by the site once to check up on work - after the trusses were installed - Assistant to GC has only been on site to check on work five times - once was after a leak - Not much supervision of subs - Communication lackluster - Inconsistent notice of subcontractors arriving onsite - sometimes no notice and sometimes just 15 minute notice - Broken Sewer Line - blowout line crushed by one of the haul off trucks or the lift equipment - Subcontractors - contractor shit in our backyard - dog was eating something and noticed the roll of toilet paper - contractors peeing in our driveway - contractor puked in the yard because he came hungover - left food trash in buckets upstairs that caused am indoor bug infestation - had to drive over to GA to confirm quartz because couldn't get what was promised - didn't communicate the schluter was horizontal and not vertical - didn't fix cut drywall in downstairs bathroom for quite some time - left it open and we taped the piece back into it - had contractors on site past normal working hours - Contractor fishing in pond putting fish in bucket - Requested payment before work was completed - saying that you had 'had a lot of money' out there - promised to charge costs on materials - no accountability on the arrival or departure times of subs. ## Craftsmanship - studio left without hardware for three months - leaking seal on pipe that ran into the wall and stained the ceiling on the floor below in both the den and downstairs bathroom - hot water install mixed with cold water so we didn't have cold water for a couple days - covered existing electrical outlets - didn't seal off area of drywall sanding - no ventilation or air treatment - installed tile inset the wrong direction - left hvac ducts unpatched for months. I finally patched them. - poured water under the house instead of piping it out - left a pile of debris in the yard for three months - left the old sliding door in the yard for a month - we personally hauled off several loads of trash - popcorn ceiling has visible seam - drywall not consistent or square in spots - dropping drywall at hvac intake - not square where the corners meet - didn't use the waterproof type throughout the bathroom - made patches where it should have been an entire board replaced - only partial bathroom in water resistant - ripped out a closet that didn't need to be removed - threw away good materials and unnecessary demo - duct vents, bi-fold doors - broke glass into the yard by tossing shower doors over the ledge - didn't plug the two HVAC vents that were ducted into the closed ceiling - found a previously split truss just one truss back from what was installed - left the extra truss in our yard for nine months - didn't patch the ceiling until months after the trusses installed - $600 heating cost to heat ceiling area - don't clean up after work - trash/food in yard, nails/metal in bushes - paint on window hardware - paint on tile floor - had to repaint and drywall because of poor work - didn't install backing support for grab bar - spilled a heavy amount of paint thinner into the subfloor which then permeated the house for a week causing headaches and eye irritation. So potent that any heating element like our oven on the first floor gave off a lighter fluid smell for a week. - put the new carpet down before the contractors had finished the other work ## Billing - quotes and invoicing incomplete - requested payment before work was completed - no discussion of invoicing changes