--- title: Issues image: https://davidawindham.com/wha/helene-1.jpg draft: true --- # Issues We've had some hiccups along the way, so I just wanted to start list of issues we've had with the general contractor and sub contractors so they're not forgotten in case we need it. **Management** - General contractor has only been by the site once to check up on work - after the trusses were installed - Assistant to GC has only been by four times - got upset when we requested that a sub look at the broken sewer line - Not much supervision of subs - Communication lackluster - quotes and invoicing incomplete - requested payment before work was completed - Inconsistent notice of subcontractors arriving onsite - sometimes no notice and sometimes just 15 minute notice - Timeliness - slow pace - some contractors will work for just a couple of hours a day for a week. - Broken Sewer Line - blowout line crushed by one of the haul off trucks or the lift equipment - Subcontractors - contractor shit in our backyard - dog was eating something and noticed the roll of toilet paper - contractors peeing in our driveway - contractor puked in the yard because he came hungover - left food trash in buckets upstairs that caused a bug infestation - had to drive over to GA to confirm quartz because couldn't get what was promised - didn't communicate the schluter was horizontal and not vertical - didn't fix cut drywall in downstairs bathroom for quite some time - left it open and we taped the piece back into it **Craftsmanship** - leaking seal on pipe that ran into the wall and stained the ceiling on the floor below in both the den and downstairs bathroom - hot water install mixed with cold water so we didn't have cold water for a couple days - poured water under the house instead of piping it out - left a pile of debris in the yard for three months - left the old sliding door in the yard for a month - we personally hauled off several loads of trash - drywall not consistent or square in spots - dropping drywall at hvac intake - not square where the corners meet - didn't use the waterproof type throughout the bathroom - made patches where it should have been an entire board replaced - ripped out a closet that didn't need to be removed - threw away good materials and unnecessary demo - duct vents, bi-fold doors - broke glass into the yard by tossing shower doors over the ledge - didn't plug the two HVAC vents that were ducted into the closed ceiling - didn't patch the ceiling until months after the trusses installed - $600 heating cost to heat ceiling area - don't clean up after work - sawdust in the drive - trash in yard - broken hardware on bifold doors - paint on tile floor - had to repaint and drywall because of poor work - didn't install backing support for grab bar - spilled a heavy amount of paint thinner into the subfloor which then permeated the house for a week causing headaches and eye irritation. So potent that any heating element like our oven on the first floor gave off a lighter fluid smell for a week. **Costs** - Requested payment before work was completed - saying that y'all 'had a lot of money' out there - promised to charge costs on materials