These are the dates of the work performed on site

KL Timmerman Enterprises, LLC

log | costs | notes

Log

|date|who|hrs|*notes| |--|--|--|--| |25/11/04 | removed extra truss|.5|| |25/11/03 | removed extra doors|.5|| |25/10/21 | Glen - chimey cap|2|| |25/10/20 | Ed - grab bars|2|| |25/10/17 | Ken - grab bars|1|| |25/10/15 | chimney/chaise caps measure|1|| |25/10/14 | painters - caulk/paint touchup|2|| |25/10/13 | glass/mirror|3|| |25/10/13 | painters - caulk/paint touchup|5|| |25/10/10 | Ed - Trimwork|5|| |25/10/09 | Ed - Trimwork|5|| |25/10/09 | HVAC ductwork & vents|3|| |25/09/29 | electricians|3|| |25/09/28 | electricians|2|| |25/09/26 | carpet install|7|| |25/09/25 | carpet install|5|| |25/09/24 | gutter install|8|| |25/09/23 | subfloor install|4|| |25/09/23 | gutter removal|3|| |25/09/22 | subfloor demo|3|| |25/09/18 | countertop install|3|| |25/09/18 | glass measure / GC by|1|| |25/09/17 | gutter guy by to measure again|1|| |25/09/08 | carpenter dressing room drawers|5|| |25/09/05 | bath counter measure|1|| |25/09/05 | - painters ( exterior - second finish )|2|| |25/09/04 | - painters ( interior )|4|| |25/09/03 | - painters ( interior )|4|| |25/09/02 | painters ( interior )|3|| |25/09/03 | plumbing ( *downstairs bathroom fix )||(separate vendor/invoice)| |25/08/28 | - carpenter - dressing Room|4|| |25/08/27 | carpenter - dressing Room|3|| |25/08/26 | plumbing Tankless & Fix hot water issue|2|| |25/08/25 | electrician crawlspace tankless|2|| |25/08/15,18 | plumbing/CPW - Tankless|3|| |25/08/04-8 | painters|3|| |25/07/28-29 | doors/Trim|3|| |25/07/21-23 | tile install Bathroom|7|| |24/07/17 | sliding Door Installation & drywall finishing|5|| |24/07/14-15 | drywall & insulation|5|| |24/07/10-11 | exterior paint|3|| |25/07/10 | electrician - adjust hall outlet|2|| |25/07/07 | - drywall Mud ( 2 days ) / Adjust kneewall|4|| |24/07/02 | drywall up|5|| |25/06/30-1 | electrical|2|| |25/06/26 | electrician/GC on site meeting|1|| |25/06/20 | plumbers|3|| |25/06/18 | plumbers - Austin & Christian|3|| |25/06/17 | plumbers - Harvey & Austin |2|| |25/06/03 | Quarle's / Snead's supply shopping|1|| |25/06/11 | - Demo|4|| |25/06/10 | - Demo|5|| |25/06/04-11 | - Demo|5|| |25/06/03-11 | - Demo|6|| |25/06/02-11 | Demo Tank & Austin (x2) ( 4.5 days 2,3,4,10,11 )||| |25/04/10 | roofer roof replaced - 7am -> 6pm - finished |9|| |25/03/27 | - cabinets(downstairs)|4|| |25/03/26 | cabinets(downstairs) installed|5|| |25/03/19 | glass measure|1|| |25/03/18 | Beth over for walkthrough mockup|1|| |25/03/19 | - Framing (x4) crew|4|| |25/03/18 | - Framing (x4) crew|6|| |25/03/17 | - Framing (x4) crew|7|| |25/03/13 | - Framing (x4) crew|5|| |25/03/12 | - Framing (x4) crew|6|| |25/03/11 | - Framing (x4) crew|7|| |25/03/10 | Framing crew - trusses installed / siding repaired|4|| |25/02/28 | received final mockup of the remodel from Beth |n/a|| |25/02/12 | cabinet guy over for measurements|1|| |25/02/06 | trusses delivered|1|| |24/11/13 | Beth over for design measurements|1|| |24/11/11 | truss measurements||| |24/11/06 | demo for truss measurements|3|| |24/10/28 | Ken and Insurance Adjuster meet|2|| |||| |TOTAL| DAYS|HOURS| ||75 Days|241 Hours|