renovations wrap

windhamdavid 5 days ago
parent
commit
99471f7ee0

+ 7 - 1
notes/house/kl-timmerman-costs.md

@@ -10,10 +10,16 @@ hide_table_of_contents: true
 
 
 
 
 
 
-These are the cost related to the hurrican helene [repairs](/notes/house/helene) and post helene renovations on the [studio](/notes/house/studio), master, and [bath](/notes/house/bath). Here are links to the .pdfs for the original [Estimates](/pdf/KLTimmerman-Estimates.pdf) and [Invoices](/pdf/KLTimmerman-Invoices.pdf). I'm using this page to share some questions and comments with the contractor and the boss.
+I'm using this page to share some questions and comments with the contractor and the boss.. These are the cost related to the hurrican helene [repairs](/notes/house/helene) and post helene renovations on the [studio](/notes/house/studio), master, and [bath](/notes/house/bath). Here are links to the .pdfs for the original [Estimates](/pdf/KLTimmerman-Estimates.pdf) and [Invoices](/pdf/KLTimmerman-Invoices.pdf). Here is the work [log](/notes/house/kl-timmerman-log).
 
 
 ## KL Timmerman Enterprises, LLC 
 ## KL Timmerman Enterprises, LLC 
 
 
+[log](/notes/house/kl-timmerman-log)
+| [costs](/notes/house/kl-timmerman-costs)
+| [estimates](/pdf/KLTimmerman-Estimates.pdf)
+| [invoices](/pdf/KLTimmerman-Invoices.pdf)
+| [issues](/notes/house/)
+
 ### Invoice(s)  # 35435 / # 35457 / # 35663 / # 35701
 ### Invoice(s)  # 35435 / # 35457 / # 35663 / # 35701
 
 
 ||Downstairs Office - Invoice # 35435|||
 ||Downstairs Office - Invoice # 35435|||

+ 92 - 92
notes/house/kl-timmerman-issues.md

@@ -9,98 +9,26 @@ draft: true
 
 
 :::
 :::
 
 
-These are our notes related to the hurrican helene [repairs](/notes/house/helene) and post helene renovations on the [studio](/notes/house/studio), master, and [bath](/notes/house/bath). I'm using this page to share some questions and comments with the contractor and the boss. We've also started a document for the contractor [costs](/notes/house/kl-timmerman-costs).
+These are our notes related to the hurrican helene [repairs](/notes/house/helene) and post helene renovations on the [studio](/notes/house/studio), master, and [bath](/notes/house/bath). I'm using this page to share some questions and comments with the contractor and the boss.
 
 
 
 
-## KL Timmerman Enterprises, LLC 
-
-## Quality Control Issues
+## Quality Control
 
 
 We've had some hiccups along the way, so I just wanted to start list of issues we've had with the general contractor and sub contractors so they're not forgotten if we need to reference them.
 We've had some hiccups along the way, so I just wanted to start list of issues we've had with the general contractor and sub contractors so they're not forgotten if we need to reference them.
 
 
-## Punch List
-
-**Exterior**
-- rear upper deck & railings
-  - ~~deck light~~
-- ~~chimney seal, cap, & wrap~~
-- caps on doubled 2x12s
-  - was told they would be caulked to look like 4x12s
-- insulation and pipes in crawlspace
-- gap sealant on gas exhaust
-- proper drainage valves on hot water heater?
-- gutters left metal intact from previous gutters
-  - leaving visible gaps under the shingles that are large enough that small critters could enter the attic. 
-  - ~~missing downspouts on gutters~~
-  - ~~hole in gutter to right of entrance~~
-  - water dripping along wood under upper gutter.
-  - ~~leaking downspout connector entrance~~
-- painting in spots
-  - siding
-  - paint spills on porch, side of house, and upper deck
-- front doors - were measured but not follow up
-- ~~haul off~~
-  - ~~truss & doors~~
-  - ~~ladder from painters~~
-- replace 3 gallons of exterior paint ๐Ÿ‘ˆ๐Ÿป
-
-**Interior**
-
-- bathroom hardware
-  - ~~shower handrails~~
-- ~~hvac ductwork~~ 
-- ~~broken shower wand tube~~
-- ~~bad water pressure~~
-  - ~~remove water restrictors?~~
-  - check sewer leak?
-  - had failed to clean out heads on faucets.
-- bathtub not properly installed ๐Ÿ‘ˆ๐Ÿป
-  - slides around
-    - no blocking as specified in manual
-  - no additional 2x12s as specified in manual
-  - no backsplash or water proofing on the wall of bathtub ๐Ÿ‘ˆ๐Ÿป
-  - white caulk on bathtub filler
-- sliding door not caulked
-  - sliding poor trim paint/stain
-- ~~ceiling fan~~
-- paint on tile floor
-- ~~no backing support for grab bars behind tile~~
-  - ~~broken grab bar install~~
-- damaged bi-fold doors
-  - broken hardware on bifold doors
-  - split wood on the base of closet doors
-- door hardware for bedroom
-- cracked floor trim from carpet puller
-- ~~closet shelves needs to be split for attic~~
-  - didn't closet shelves
-- ~~carpet doesn't meet baseboards~~
-  - carpet transition to tile ๐Ÿ‘ˆ๐Ÿป
-  - ~~feel tacks on bare feet~~
-- dressing room 
-  - drawers/hardware
-  - stained seat top
-  - lighting? extra switch? ๐Ÿ‘ˆ๐Ÿป
-  - ~~bathroom switches upside down~~
-  - ~~stairway light switch~~
-- lots of questionable drywall/paint work ๐Ÿ‘ˆ๐Ÿป
-  - crooked wall in bedroom corner
-  - tape marks in ceiling
-  - wavy at bed entrance - too many repair pieces
-  - splotchy above bed
-  - spots on bathroom ceiling
-- downstairs ceiling repair from two separate leaks and jackhammer cracking ๐Ÿ‘ˆ๐Ÿป
-- downstairs bathroom paint ๐Ÿ‘ˆ๐Ÿป
-- stairwell trim paint baseboards
-
-
-**Minor**
-- window treatments 
-  - tub / vertical blinds
-  - remove curtain rod
+## KL Timmerman Enterprises, LLC 
 
 
+[log](/notes/house/kl-timmerman-log)
+| [costs](/notes/house/kl-timmerman-costs)
+| [estimates](/pdf/KLTimmerman-Estimates.pdf)
+| [invoices](/pdf/KLTimmerman-Invoices.pdf)
+| [issues](/notes/house/)
 
 
 ## Management
 ## Management
 
 
+- Showed up on site unannounced requesting payment before work was completed or inspected
+- Invoicing duplicate errors
+  - No discussion of invoices
 - Timeliness 
 - Timeliness 
   - slow pace - some contractors will work for just a couple of hours a day for a week.
   - slow pace - some contractors will work for just a couple of hours a day for a week.
   - took **over a year** to complete the project or **9 months** if you account for the truss manufacturing delay
   - took **over a year** to complete the project or **9 months** if you account for the truss manufacturing delay
@@ -140,7 +68,6 @@ We've had some hiccups along the way, so I just wanted to start list of issues w
   - no ventilation or air treatment
   - no ventilation or air treatment
   - didn't replace hvac intakes
   - didn't replace hvac intakes
 - installed tile inset the wrong direction
 - installed tile inset the wrong direction
-- left hvac ducts unpatched for months. I finally patched them.
 - poured water under the house instead of piping it out
 - poured water under the house instead of piping it out
 - left a pile of debris in the yard for three months
 - left a pile of debris in the yard for three months
 - left the old sliding door in the yard for a month
 - left the old sliding door in the yard for a month
@@ -151,13 +78,16 @@ We've had some hiccups along the way, so I just wanted to start list of issues w
   - not square where the corners meet
   - not square where the corners meet
   - didn't use the waterproof type throughout the bathroom
   - didn't use the waterproof type throughout the bathroom
   - made patches where it should have been an entire board replaced
   - made patches where it should have been an entire board replaced
+  - bubbles showing through the paint
 - ripped out a closet that didn't need to be removed
 - ripped out a closet that didn't need to be removed
 - threw away good materials and unnecessary demo
 - threw away good materials and unnecessary demo
-  - duct vents, bi-fold doors
+  - duct vents & bi-fold doors
+  - replaced solid wood closet and room doors with lesser quality
 - broke glass into the yard by tossing shower doors over the ledge
 - broke glass into the yard by tossing shower doors over the ledge
 - didn't plug the two HVAC vents that were ducted into the closed ceiling
 - didn't plug the two HVAC vents that were ducted into the closed ceiling
 - found a previously split truss just one truss back from what was installed
 - found a previously split truss just one truss back from what was installed
-  - didn't mention it to us
+  - noticed but didn't mention it to us or offer to replace
+    - given we had ordered one additional truss that was left at our house
 - left the extra truss in our yard for nine months
 - left the extra truss in our yard for nine months
 - didn't patch the ceiling until months after the trusses installed
 - didn't patch the ceiling until months after the trusses installed
   - $600 heating cost to heat ceiling area
   - $600 heating cost to heat ceiling area
@@ -170,14 +100,84 @@ We've had some hiccups along the way, so I just wanted to start list of issues w
 - had to repaint and drywall because of poor work
 - had to repaint and drywall because of poor work
 - didn't install backing support for grab bar
 - didn't install backing support for grab bar
 - spilled a heavy amount of paint thinner into the subfloor which then permeated the house for a week causing headaches and eye irritation. So potent that any heating element like our oven on the first floor gave off a lighter fluid smell for a week.
 - spilled a heavy amount of paint thinner into the subfloor which then permeated the house for a week causing headaches and eye irritation. So potent that any heating element like our oven on the first floor gave off a lighter fluid smell for a week.
+- window treatments 
+  - tub / vertical blinds
+  - remove curtain rod
 - put the new carpet down before the contractors had finished the other work
 - put the new carpet down before the contractors had finished the other work
   - carpet has visable seams
   - carpet has visable seams
   - carpet doesn't extent far enough under baseboards
   - carpet doesn't extent far enough under baseboards
 
 
-## Billing
+## Punch List
+
+**Exterior**
+- rear upper deck & railings
+  - ~~deck light~~
+- ~~chimney seal, cap, & wrap~~
+- caps on doubled 2x12s
+  - was told they would be caulked to look like 4x12s
+- insulation and pipes in crawlspace
+- gap sealant on gas exhaust
+- proper drainage valves on hot water heater?
+- gutters left metal intact from previous gutters
+  - leaving visible gaps under the shingles that are large enough that small critters could enter the attic. 
+  - ~~missing downspouts on gutters~~
+  - ~~hole in gutter to right of entrance~~
+  - water dripping along wood under upper gutter.
+  - ~~leaking downspout connector entrance~~
+- painting in spots
+  - siding
+  - paint spills on porch, side of house, and upper deck
+- front doors - were measured but not follow up
+- ~~haul off~~
+  - ~~truss & doors~~
+  - ~~ladder from painters~~
+- replace 3 gallons of exterior paint ๐Ÿ‘ˆ๐Ÿป
+
+**Interior**
+
+- bathroom hardware
+  - ~~shower handrails~~
+- ~~hvac ductwork~~ 
+- ~~broken shower wand tube~~
+- ~~bad water pressure~~
+  - ~~remove water restrictors?~~
+  - check sewer leak?
+  - had failed to clean out heads on faucets.
+- bathtub not properly installed ๐Ÿ‘ˆ๐Ÿป
+  - slides around
+    - no blocking as specified in manual
+  - no additional 2x12s as specified in manual
+  - no backsplash or water proofing on the wall of bathtub ๐Ÿ‘ˆ๐Ÿป
+  - white caulk on bathtub filler
+- sliding door not caulked
+  - sliding poor trim paint/stain
+- ~~ceiling fan~~
+- paint on tile floor
+- ~~no backing support for grab bars behind tile~~
+  - ~~broken grab bar install~~
+- damaged bi-fold doors
+  - broken hardware on bifold doors
+  - split wood on the base of closet doors
+- door hardware for bedroom
+- cracked floor trim from carpet puller
+- ~~closet shelves needs to be split for attic~~
+  - didn't closet shelves
+- ~~carpet doesn't meet baseboards~~
+  - carpet transition to tile ๐Ÿ‘ˆ๐Ÿป
+  - ~~feel tacks on bare feet~~
+- dressing room 
+  - drawers/hardware
+  - stained seat top
+  - lighting? extra switch? ๐Ÿ‘ˆ๐Ÿป
+  - ~~bathroom switches upside down~~
+  - ~~stairway light switch~~
+- lots of questionable drywall/paint work ๐Ÿ‘ˆ๐Ÿป
+  - crooked wall in bedroom corner
+  - tape marks in ceiling
+  - wavy at bed entrance - too many repair pieces
+  - splotchy above bed
+  - spots on bathroom ceiling
+- downstairs ceiling repair from two separate leaks and jackhammer cracking ๐Ÿ‘ˆ๐Ÿป
+- downstairs bathroom paint ๐Ÿ‘ˆ๐Ÿป
+- stairwell trim paint baseboards
 
 
-- quotes and invoicing inconsistent. 
-- Showed up on site requesting payment before work was completed or inspected
-- No discussion of invoicing changes
-- Invoicing duplicate errors
-- aggressive labor charges

+ 105 - 0
notes/house/kl-timmerman-log.md

@@ -0,0 +1,105 @@
+---
+title: Renovation Log
+image: https://davidawindham.com/wha/helene-1.jpg
+hide_table_of_contents: true
+---
+
+# Renovation Log
+
+:::warning[Private Page]
+
+:::
+
+These are the dates of the work performed on site
+
+
+
+## KL Timmerman Enterprises, LLC 
+
+[log](/notes/house/kl-timmerman-log)
+| [costs](/notes/house/kl-timmerman-costs)
+| [estimates](/pdf/KLTimmerman-Estimates.pdf)
+| [invoices](/pdf/KLTimmerman-Invoices.pdf)
+| [issues](/notes/house/)
+
+## Log
+
+|date|who|hrs|*notes|
+|--|--|--|--|
+|**25/11/04**    | removed extra truss|.5||
+|**25/11/03**    | removed extra doors|.5||
+|**25/10/21**    | Glen - chimey cap|2||
+|**25/10/20**    | Ed - grab bars|2||
+|**25/10/17**    | Ken - grab bars|1||
+|**25/10/15**    | chimney/chaise caps measure|1||
+|**25/10/14**    | painters - caulk/paint touchup|2||
+|**25/10/13**    | glass/mirror|3||
+|**25/10/13**    | painters - caulk/paint touchup|5||
+|**25/10/10**    | Ed - Trimwork|5||
+|**25/10/09**    | Ed - Trimwork|5||
+|**25/10/09**    | HVAC ductwork & vents|3||
+|**25/09/29**    | electricians|3||
+|**25/09/28**    | electricians|2||
+|**25/09/26**    | carpet install|7||
+|**25/09/25**    | carpet install|5||
+|**25/09/24**    | gutter install|8||
+|**25/09/23**    | subfloor install|4||
+|**25/09/23**    | gutter removal|3||
+|**25/09/22**    | subfloor demo|3||
+|**25/09/18**    | countertop install|3||
+|**25/09/18**    | glass measure / GC by|1||
+|**25/09/17**    | gutter guy by to measure again|||
+|**25/09/08**    | carpenter dressing room drawers|||
+|**25/09/05**    | bath counter measure|||
+|**25/09/05**    | - painters ( exterior - second finish )|||
+|**25/09/04**    | - painters ( interior )|||
+|**25/09/03**    | - painters ( interior )|||
+|**25/09/02**    | painters ( interior )|||
+|**25/09/03**    | plumbing ( *downstairs bathroom fix )||(separate vendor/invoice)|
+|**25/08/28**    | - carpenter - dressing Room|||
+|**25/08/27**    | carpenter - dressing Room|||
+|**25/08/26**    | plumbing Tankless & Fix hot water issue|||
+|**25/08/25**    | electrician crawlspace tankless|5||
+|**25/08/15,18** | plumbing/CPW - Tankless|||
+|**25/08/04-8**  | painters|||
+|**25/07/28-29** | doors/Trim|||
+|**25/07/21-23** | tile install Bathroom|||
+|**24/07/17**    | sliding Door Installation & drywall finishing|||
+|**24/07/14-15** | drywall & insulation|||
+|**24/07/10-11** | exterior paint|||
+|**25/07/10**    | electrician - adjust hall outlet|||
+|**25/07/07**    | - drywall Mud ( 2 days ) / Adjust kneewall|||
+|**24/07/02**    | drywall up|||
+|**25/06/30-1**  | electrical|||
+|**25/06/26**    | electrician/GC on site meeting|||
+|**25/06/20**    | plumbers|||
+|**25/06/18**    | plumbers - Austin & Christian|||
+|**25/06/17**    | plumbers - Harvey & Austin |||
+|**25/06/03**    | Quarle's / Snead's supply shopping|||
+|**25/06/11**    | - Demo|||
+|**25/06/10**    | - Demo|||
+|**25/06/04-11** | - Demo|||
+|**25/06/03-11** | - Demo|||
+|**25/06/02-11** | Demo Tank & Austin (x2) ( 4.5 days 2,3,4,10,11 )|||
+|**25/04/10**    | roofer roof replaced - 7am -> 6pm - finished |||
+|**25/03/27**    | - cabinets|||
+|**25/03/26**    | cabinets installed|||
+|**25/03/19**    | glass measure|||
+|**25/03/18**    | Beth over for walkthrough mockup|||
+|**25/03/19**    | - Framing (x4) crew|||
+|**25/03/18**    | - Framing (x4) crew|||
+|**25/03/17**    | - Framing (x4) crew|||
+|**25/03/13**    | - Framing (x4) crew|||
+|**25/03/12**    | - Framing (x4) crew|||
+|**25/03/11**    | - Framing (x4) crew|||
+|**25/03/10**    | Framing crew - trusses installed / siding repaired|||
+|**25/02/28**    | received final mockup of the remodel from Beth |||
+|**25/02/12**    | cabinet guy over for measurements|||
+|**25/02/06**    | trusses delivered|||
+|**24/11/13**    | Beth over for design measurements|||
+|**24/11/11**    |  truss measurements|||
+|**24/11/06**    | demo for truss measurements|3||
+|**24/10/28**    | Ken and Insurance Adjuster meet|2||
+||||
+|**TOTAL**| **DAYS**|**HOURS**|
+||||