|
@@ -6,66 +6,120 @@ draft: true
|
|
|
|
|
|
# Issues
|
|
# Issues
|
|
|
|
|
|
-We've had some hiccups along the way, so I just wanted to start list of issues we've had with the general contractor and sub contractors so they're not forgotten in case we need it.
|
|
|
|
|
|
+We've had some hiccups along the way, so I just wanted to start list of issues we've had with the general contractor and sub contractors so they're not forgotten when we need to reference them.
|
|
|
|
|
|
-**Management**
|
|
|
|
-- General contractor has only been by the site once to check up on work - after the trusses were installed
|
|
|
|
-- Assistant to GC has only been by four times
|
|
|
|
- - got upset when we requested that a sub look at the broken sewer line
|
|
|
|
|
|
+## Punch List
|
|
|
|
+
|
|
|
|
+**Exterior**
|
|
|
|
+- rear upper deck & railings
|
|
|
|
+ - deck light
|
|
|
|
+- caps on doubled 2x12s
|
|
|
|
+ - was told they would be caulked to look like 4x12s
|
|
|
|
+- insulation and pipes in crawlspace
|
|
|
|
+- proper drainage pipes on hot water heater
|
|
|
|
+- chimney seal, cap, & wrap
|
|
|
|
+- gutters left metal intact from previous gutters
|
|
|
|
+ - leaving visable gaps under the shingles that are large enough that small critters could enter the attic.
|
|
|
|
+- missing downspouts on gutters
|
|
|
|
+- hole in gutter to right of entrance
|
|
|
|
+- water dripping along wood under upper gutter.
|
|
|
|
+- leaking downspout connector entrance
|
|
|
|
+- painting in spots
|
|
|
|
+- front doors - were measured but not follow up
|
|
|
|
+
|
|
|
|
+**Interior**
|
|
|
|
+- missing closet lights
|
|
|
|
+- hvac ductwork
|
|
|
|
+- damaged sliding doors
|
|
|
|
+- broken hardware on bifold doors
|
|
|
|
+- door hardware for bedroom
|
|
|
|
+- missing foot boards and crown molding
|
|
|
|
+- crooked wall in bedroom corner
|
|
|
|
+- lots of bad drywall work
|
|
|
|
+ - tape marks in ceiling
|
|
|
|
+- sliding door not caulked
|
|
|
|
+- broken shower wand tube
|
|
|
|
+- downstairs ceiling repair from two separate leaks and jackhammer cracking
|
|
|
|
+- downstairs bathroom paint
|
|
|
|
+- bathtub not properly installed
|
|
|
|
+ - slides around
|
|
|
|
+- no backsplash or water proofing on the wall of bathtub
|
|
|
|
+- white caulk on bathtub faucet
|
|
|
|
+- paint on tile floor
|
|
|
|
+- cracked floor trim from carpet puller
|
|
|
|
+
|
|
|
|
+## Management
|
|
|
|
+
|
|
|
|
+- Timeliness
|
|
|
|
+ - slow pace - some contractors will work for just a couple of hours a day for a week.
|
|
|
|
+ - took **over a year** to complete the project
|
|
|
|
+- General contractor has only been by the site once to check up on work
|
|
|
|
+ - after the trusses were installed
|
|
|
|
+- Assistant to GC has only been on site to check on work five times
|
|
|
|
+ - once was after a leak
|
|
- Not much supervision of subs
|
|
- Not much supervision of subs
|
|
- Communication lackluster
|
|
- Communication lackluster
|
|
- - quotes and invoicing incomplete
|
|
|
|
- - requested payment before work was completed
|
|
|
|
- Inconsistent notice of subcontractors arriving onsite
|
|
- Inconsistent notice of subcontractors arriving onsite
|
|
- sometimes no notice and sometimes just 15 minute notice
|
|
- sometimes no notice and sometimes just 15 minute notice
|
|
-- Timeliness
|
|
|
|
- - slow pace - some contractors will work for just a couple of hours a day for a week.
|
|
|
|
- Broken Sewer Line
|
|
- Broken Sewer Line
|
|
- blowout line crushed by one of the haul off trucks or the lift equipment
|
|
- blowout line crushed by one of the haul off trucks or the lift equipment
|
|
- Subcontractors
|
|
- Subcontractors
|
|
- contractor shit in our backyard - dog was eating something and noticed the roll of toilet paper
|
|
- contractor shit in our backyard - dog was eating something and noticed the roll of toilet paper
|
|
- contractors peeing in our driveway
|
|
- contractors peeing in our driveway
|
|
- contractor puked in the yard because he came hungover
|
|
- contractor puked in the yard because he came hungover
|
|
- - left food trash in buckets upstairs that caused a bug infestation
|
|
|
|
|
|
+ - left food trash in buckets upstairs that caused am indoor bug infestation
|
|
- had to drive over to GA to confirm quartz because couldn't get what was promised
|
|
- had to drive over to GA to confirm quartz because couldn't get what was promised
|
|
- didn't communicate the schluter was horizontal and not vertical
|
|
- didn't communicate the schluter was horizontal and not vertical
|
|
- didn't fix cut drywall in downstairs bathroom for quite some time
|
|
- didn't fix cut drywall in downstairs bathroom for quite some time
|
|
- left it open and we taped the piece back into it
|
|
- left it open and we taped the piece back into it
|
|
- had contractors on site past normal working hours
|
|
- had contractors on site past normal working hours
|
|
- - once until almost dark (7:30pm 9/22 subfloor) sawing
|
|
|
|
-
|
|
|
|
|
|
+- Contractor fishing in pond putting fish in bucket
|
|
|
|
+- Requested payment before work was completed
|
|
|
|
+ - saying that you had 'had a lot of money' out there
|
|
|
|
+- promised to charge costs on materials
|
|
|
|
+- no accountability on the arrival or departure times of subs.
|
|
|
|
|
|
-**Craftsmanship**
|
|
|
|
|
|
+## Craftsmanship
|
|
|
|
|
|
|
|
+- studio left without hardware for three months
|
|
- leaking seal on pipe that ran into the wall and stained the ceiling on the floor below in both the den and downstairs bathroom
|
|
- leaking seal on pipe that ran into the wall and stained the ceiling on the floor below in both the den and downstairs bathroom
|
|
- hot water install mixed with cold water so we didn't have cold water for a couple days
|
|
- hot water install mixed with cold water so we didn't have cold water for a couple days
|
|
|
|
+- covered existing electrical outlets
|
|
|
|
+- didn't seal off area of drywall sanding
|
|
|
|
+ - no ventilation or air treatment
|
|
|
|
+- installed tile inset the wrong direction
|
|
|
|
+- left hvac ducts unpatched for months. I finally patched them.
|
|
- poured water under the house instead of piping it out
|
|
- poured water under the house instead of piping it out
|
|
- left a pile of debris in the yard for three months
|
|
- left a pile of debris in the yard for three months
|
|
- left the old sliding door in the yard for a month
|
|
- left the old sliding door in the yard for a month
|
|
- we personally hauled off several loads of trash
|
|
- we personally hauled off several loads of trash
|
|
|
|
+- popcorn ceiling has visible seam
|
|
- drywall not consistent or square in spots
|
|
- drywall not consistent or square in spots
|
|
- dropping drywall at hvac intake
|
|
- dropping drywall at hvac intake
|
|
- not square where the corners meet
|
|
- not square where the corners meet
|
|
- didn't use the waterproof type throughout the bathroom
|
|
- didn't use the waterproof type throughout the bathroom
|
|
- made patches where it should have been an entire board replaced
|
|
- made patches where it should have been an entire board replaced
|
|
|
|
+ - only partial bathroom in water resistant
|
|
- ripped out a closet that didn't need to be removed
|
|
- ripped out a closet that didn't need to be removed
|
|
- threw away good materials and unnecessary demo
|
|
- threw away good materials and unnecessary demo
|
|
- duct vents, bi-fold doors
|
|
- duct vents, bi-fold doors
|
|
- broke glass into the yard by tossing shower doors over the ledge
|
|
- broke glass into the yard by tossing shower doors over the ledge
|
|
- didn't plug the two HVAC vents that were ducted into the closed ceiling
|
|
- didn't plug the two HVAC vents that were ducted into the closed ceiling
|
|
|
|
+- found a previously split truss just one truss back from what was installed
|
|
|
|
+- left the extra truss in our yard for nine months
|
|
- didn't patch the ceiling until months after the trusses installed
|
|
- didn't patch the ceiling until months after the trusses installed
|
|
- $600 heating cost to heat ceiling area
|
|
- $600 heating cost to heat ceiling area
|
|
- don't clean up after work
|
|
- don't clean up after work
|
|
- - sawdust in the drive
|
|
|
|
- - trash in yard
|
|
|
|
-- broken hardware on bifold doors
|
|
|
|
|
|
+ - trash/food in yard, nails/metal in bushes
|
|
|
|
+- paint on window hardware
|
|
- paint on tile floor
|
|
- paint on tile floor
|
|
- had to repaint and drywall because of poor work
|
|
- had to repaint and drywall because of poor work
|
|
- didn't install backing support for grab bar
|
|
- didn't install backing support for grab bar
|
|
- spilled a heavy amount of paint thinner into the subfloor which then permeated the house for a week causing headaches and eye irritation. So potent that any heating element like our oven on the first floor gave off a lighter fluid smell for a week.
|
|
- spilled a heavy amount of paint thinner into the subfloor which then permeated the house for a week causing headaches and eye irritation. So potent that any heating element like our oven on the first floor gave off a lighter fluid smell for a week.
|
|
|
|
+- put the new carpet down before the contractors had finished the other work
|
|
|
|
|
|
-**Costs**
|
|
|
|
|
|
+## Billing
|
|
|
|
|
|
-- Requested payment before work was completed
|
|
|
|
- - saying that y'all 'had a lot of money' out there
|
|
|
|
-- promised to charge costs on materials
|
|
|
|
|
|
+- quotes and invoicing incomplete
|
|
|
|
+ - requested payment before work was completed
|
|
|
|
+ - no discussion of invoicing changes
|