  1. 204 0
      notes/house/kl-timmerman-costs.md
  2. 59 50
      notes/house/kl-timmerman-issues.md

+ 204 - 0
notes/house/kl-timmerman-costs.md

@@ -0,0 +1,204 @@
+---
+title: Renovation Costs
+image: https://davidawindham.com/wha/helene-1.jpg
+hide_table_of_contents: true
+---
+
+:::warning[Private Page]
+
+:::
+
+
+
+These are the cost related to the hurrican helene [repairs](/notes/house/helene) and post helene renovations on the [studio](/notes/house/studio), master, and [bath](/notes/house/bath). Here are links to the .pdfs for the original [Estimates](/pdf/KLTimmerman-Estimates.pdf) and [Invoices](/pdf/KLTimmerman-Invoices.pdf). I'm using this page to share some questions and comments with the contractor and the boss. We've also started a document for the remaining quality control [issues](/notes/house/kl-timmerman-issues).
+
+## KL Timmerman Enterprises, LLC 
+
+### Invoice(s)  # 35435 / # 35457 / # 35663 / # 35701
+
+||Downstairs Office - Invoice # 35435|||
+|---|---|---|---|
+|1. Fabricate and install lower cabinets with pull out shelving for printer.||||
+||- The center will be desk area.|||
+||- Fabricate bookcases to set on top of the counter top.|||
+||* Height to be about 29 1/4". With counter top the overall height will be around 30".|||
+||* Alder wood will be used.|||
+||Labor and materials |$8,200.00||
+|2. Install smooth black Formica countertop the width of the room.||||
+||* The counter top will have 1 seam due to the length.|||
+||Labor and materials |$1,000.00||
+|3. Install an outlet for the printer.||||
+||- Install 1 quad outlet.|||
+||- Install TV outlet.|||
+||* Use existing circuit.|||
+||Labor and materials |$937.00|๐Ÿ‘ˆ๐Ÿป an outlet?|
+|||||
+||<b>TOTAL</b>|<b>$10,137.00</b>||
+|||||
+
+<div><br/><br/></div>
+
+||Roof / Siding - Invoice # 35457|||
+|---|---|---|---|
+|1. Roof trusses. ||$1,983.80||
+|2. Remove existing roof shingles, roof sheeting, overhang soffit, and trim in area of repair at upper bedroom of home.||$17,339.83||
+||- Remove four damaged 2x4 trusses.|||
+||- Replace damaged trusses.|||
+||- Install new 1/2" OSB plywood using clips in area of repair only.|||
+||- Remove existing 1/2" rough sawn plywood siding with 1x8 cedar trim boards at rear wall of bedroom including damaged area on side wall.|||
+||- Install new brick mould trim to one window unit at rear of bedroom wall.|||
+||- Install new siding and soffit trim to area of repair as to match existing as close as possible.|||
+|3. Remove existing shingles and haul away all job related debris. ||$20,522.04||
+||- Install Atlas 35 year architectural shingles to entire roof system.|||
+||- Install synthetic underlayment barrier to entire roof system.|||
+||- Install shingle over ridge vent to gable ridge of home.|||
+||- Replace all vent pipe collar boots and install new flashing at any chimneys's.|||
+|4. Hang sheetrock on ceiling at upstairs bedroom and repair closet ceiling and wall.||||
+||- Apply texture at repair area.|||
+|5. Caulk, prime, and putty one new side and touch up handrails.||||
+||- Caulk, prime, and putty soffit on both sides and siding as needed.|||
+||- Paint inside bedroom, bath, and closet ceiling, trim, and walls. Exterior $4860.00 - Interior $3071.25|||
+|6. Install approximately 114 lf og Alcoa 6" seamless aluminum guttering to the home.||||
+||- Install approximately 75lf of commercial 3 x 4 downspout to gutter system.|||
+|7. Install Sureflow 6" leaf protection to new guttering on the home.||||
+|8. Rental fee for telehandler to set roof truss and make exterior repairs. ||$3,111.45||
+|9. Furnished and installed two 5/8" clear tempered IG units. ||$1,136.00|๐Ÿ‘ˆ๐Ÿปโ‰๏ธ duplicated on addendum|
+|10. Remove existing sliding patio door unit from rear upper level of home.||||
+||- Haul away job related debris.|||
+||- Install one Weathershield Signature Series sliding patio door unit with painted aluminum clad trim.|||
+||- Interior of door unit will be unfinished wood.|||
+||- Door unit will come with Low-E performance glass units.|||
+||- Door unit will have a standard 2 point lock system with keyed lock.|||
+|11. Replace interior and window and door casing.||||
+|12. Cut out ceiling in the bedroom to assess damage and hauled off debris. ||$540.11||
+|13. Install padding and carpet.||||
+|14. Blown-in insulation in master bedroom ceiling.||||
+|15. Duct work repair/replacement. * TO BE FORTHCOING||||
+|16.  Install ceiling fan in the master bedroom - labor only||||
+||- Remove and reset the exterior light fixture by the sliding glass patio door.|||
+|||||
+||TOTAL|$44,633.23|โœ…|
+|||||
+
+<div><br/><br/></div>
+
+||Master Suite Remodel - Invoice # 35663|||
+|---|---|---|---|
+|DEMO AND ROUGH-IN CARPENTRY||||
+|1. Demo walls associated with remodel.||||
+||- Remove both shower units, vanities/tops, and plumbing fixtures.||
+||- Take up existing floor tile and subfloor to access plumbing.|||
+||Labor - range between $5000.00 - $6500.00|$5,239.44||
+||Disposal fee at landfill allowance |$0.00||
+|2. Cut and install new subfloor.|Labor |$1,363.00||
+||Materials |$416.60||
+|3. Frame new walls, install supports in shower, frame custom niche in shower.|Labor|$1,785.00||
+||Materials|$381.94||
+|PLUMBING||||
+|1. Cap lines for demo.|- Re-route water (will use Pex pipe) and drain lines for plumbing fixture locations.|||
+||- Re-route vent through the roof.|||
+||Labor and plumbing materials |$5,625.00||
+|2. Install new plumbing valves and fixtures.|Labor|$3750.00||
+|3. Install a gas tankless water heater| Labor, water heater, and plumbing materials|$3750.00||
+|Fixtures||||
+|1. Quarles quote||$3607.29||
+|2. Toilet from Quarles||$306.79||
+|3. Moen rough-in valve for shower ||$194.41||
+|4. Toilet - American Standard Aspirations 252AA899.020 * with tax ||$1,781.55|๐Ÿ‘ˆ๐Ÿป $450 from Home Depot?|
+|ELECTRICAL||||
+|Bathroom 1. Demo existing as needed.|- Install customer provided heater/fan combo outside shower area and switched on door wall opposite of shower.|||
+||- Install an outlet on the bathroom entry door wall opposite of shower.|||
+||- Install 3 wafer lights on a dimmer switch - 3 way - switch to be located on bathroom entry door wall opposite of shower and on the left end wall of vanity. * Only installed 2 wafers, added 2 retrofit can trims for stairwell.|
+||- Install 2 vanity lights - switch to be located on left end wall of vanity.|||
+||- Install 2 GFI's - to be located on left and right walls of vanity.|||
+|Master bedroom ||||
+|1. Install new ceiling fan - switch to be located on left wall entering the bedroom.|- Switch the 2 existing outlets on long wall of bedroom for lamps - switch to be located of left wall entering the bedroom.|||
+||Labor and materials |$5,225.00|๐Ÿ‘ˆ๐Ÿป|
+||Panasonic Whisper Coy heater/van 811A * Customer provided|||
+||2 vanity lights |$503.05||
+||CREDIT FOR INSTALLATION OF CEILING FAN FROM INSURANCE. |-$250.00||
+|DRYWALL|||
+||1. Make repairs to drywall from demo.|||
+||2. Install drywall on walls and ceiling associated with master bathroom and bedroom remodel.|||
+||Labor and materials |$4,620.00||
+|TRIM AND DOORS ||||
+|1. Install baseboard in the bedroom, bathroom, hallway, and Ginny's closet - all associated with remodel.|- Install bi-hinge bedroom doors and casing - 6 panel raised solid core. INSTALLED BIFOLD|||
+||- Install bi-hinge closet doors and casing - 6 panel raised solid core. INSTALLED BI-FOLD|||
+||- Install 2 door units for bathroom and casing - 6 panel raised solid core. DID NOT DO|||
+||Labor |$2,200.00||
+||Trim |$453.65||
+||Allowance - Door units, bi-hinge doors, hinges, ball catches, and door handles. |$983.75||
+||* Door allowance etc was 1200.00. Actual cost was 1585.91. Giving credit for the 2 bathroom doors 361.66. Giving credit for 1/2 of the bi-fold closet door - agreed on bi-hinge and we threw away the existing bi-fold - bought new bi-fold doors at 481.00 - will split this and gave credit for 240.50|||
+|PAINTING||||
+|1. Paint all ceilings, walls, and trim associated with master bedroom and bathroom remodel.|Labor and materials|$3,125.00||
+||-Stairwell long wall, short wall at end of landing, trim, and the ceiling - $1,312.50|||
+||- One wall, trim, and door in Ginny's closet - $593.75 * No extra charge for painting complete closet.|||
+||- Bathroom walls, ceiling, trim, and door - $1,218.75|||
+|MISCELLANEOUS||||
+|1. Shower and bathroom floor tile|Labor |$5,625.00||
+||Tile allowance for shower walls, shower floor, and outside floor * Tile cost for shower and outside floor was 3660.58|$3,660.58||
+||Freight allowance |$300.00||
+||Materials - grout, caulk, schluter, backerboard, schluter Kerdi shower tray, etc. This is included in the 3660.58 amount|||
+|2. Bedroom padding and carpet|Labor|$1,050.00||
+||- Carpet allowance and pad together was 4291.24 |$4,291.24||
+||#10 pad and seam tape|||
+||CREDIT FROM INSURANCE ON 216 s ft ALLOWANCE FOR INSURANCE.|-$1391.04||
+|3. Vanity|- Custom build and install vanity.|||
+||Allowance |$8800.00||
+||Allowance for knobs/pulls|||
+|4. Vanity top and sinks|- Template and install|||
+||Allowance for top and sinks Actual cost |$3,833.40||
+|5. Shower door TO BE ON FINAL DRAW|- Custom shower door and installation allowance. |$3000.00||
+|6. Mirror - remove existing mirror and reinstall.||$250.00|๐Ÿ‘ˆ๐Ÿปโ‰๏ธ duplicate|
+|7. Install bathroom accessories|Grab bar 50.00 each * WILL BE ON FINAL INOICE|$0.00||
+||Towel bars, robe hooks, toilet paper holder, and 2 hand towel rings.|$125.00||
+||Allowance on accessories * Cost of accessories including closet pulls |$388.64||
+|8. Allowance on custom linen closet. ||$2,500.00||
+|EXTRAS - ALL AT COST||||
+||Permit fee paid |$110.00||
+||Extra insulation |$800.00||
+||Extra quad outlets and light and switch in the crawlspace|$645.00||
+||Closet labor |$1550.00||
+||Closet materials |$739.80||
+||Painting closet and drawer fronts |$680.00||
+||Installed outside light fixture |$80.00||
+||Installed uarter round in carpeted rooms|$200.00||
+||Quarter round|$61.63||
+|9. Hung sheetrock on ceiling at upstairs bedroom and repaired closet ceiling and wall. |- Applied texture at repair area.|$2835.00|๐Ÿ‘ˆ๐Ÿป|
+|10. Caulked, primed, and puttied one new side and touched up handrails.||$7331.25|๐Ÿ‘ˆ๐Ÿปโ‰๏ธ|
+|11. Blown in insulation in master bedroom ceiling. |* This was considerably less.|$480.00||
+|||||
+||<b>TOTAL</b>|<b>$93,006.97</b>||
+|||||
+
+<div><br/><br/></div>
+
+||Addendum - Invoice # 35701|||
+|---|---|---|---|
+|Extra Items Requested||||
+|1. Installed 2 chimney caps and a custom fabricated border shade. ||$874.70||
+|2. Replaced gutters around remainder of home. ||$2,978.08||
+|3. Installed leaf protection. ||$1794.90||
+|4. Master bedroom - replaced 2 clear IG units. ||$1,336.00|๐Ÿ‘ˆ๐Ÿปโ‰๏ธ duplicate|
+|||||
+|REGARDING INVOICE #35663||||
+|1. Page 4 - Item # 5 - Shower door was invoiced at $3000.00 - Actual cost was $2918.00|- Labor and materials to install custom door. |-$82.00||
+|2. Page 4 - Item #6 - Mirror - *|- cut existing mirror and installed |$190.00|๐Ÿ‘ˆ๐Ÿปโ‰๏ธ duplicate|
+|3. Page 5 - Item #7 - install bathroom accessories|- Installed grab bar |$50.00||
+|||||
+|Remaining items from the Insurance estimate that have not been invoiced.||||
+|1. Removed existing sliding patio door unit from rear upper level.|- Installed Weathersheild unit.|||
+||Labor |$3,347.50||
+||Door unit |$3,914.62||
+|||||
+|2. Installed 114 lf of Alcoa 6" seamless gutter.||||
+||Labor and materials |$2,689.60||
+|3. Install Sureflow 6" leaf protection.||||
+||Labor and materials |$1,635.55||
+|4. Repaired/replace duct wor and connected at drops.||||
+||Labor and materials |$1,050.00||
+|||||
+||<b>TOTAL</b>|<b>$19,778.95</b>||
+|||||
+|||||
+||<b>GRAND TOTAL</b>|<b>$167,556.15</b>||

+ 59 - 50
notes/house/helene-issues.md → notes/house/kl-timmerman-issues.md

@@ -1,94 +1,102 @@
 ---
-title: Issues
+title: Renovation Issues
 image: https://davidawindham.com/wha/helene-1.jpg
+hide_table_of_contents: true
 draft: true
 ---
 
-# Issues
+:::warning[Private Page]
 
-We've had some hiccups along the way, so I just wanted to start list of issues we've had with the general contractor and sub contractors so they're not forgotten when we need to reference them.
+:::
+
+These are our notes related to the hurrican helene [repairs](/notes/house/helene) and post helene renovations on the [studio](/notes/house/studio), master, and [bath](/notes/house/bath). I'm using this page to share some questions and comments with the contractor and the boss. We've also started a document for the contractor [costs](/notes/house/kl-timmerman-costs).
+
+
+## KL Timmerman Enterprises, LLC 
+
+## Quality Control Issues
+
+We've had some hiccups along the way, so I just wanted to start list of issues we've had with the general contractor and sub contractors so they're not forgotten if we need to reference them.
 
 ## Punch List
 
 **Exterior**
 - rear upper deck & railings
   - ~~deck light~~
-- chimney seal, cap, & wrap
+- ~~chimney seal, cap, & wrap~~
 - caps on doubled 2x12s
   - was told they would be caulked to look like 4x12s
 - insulation and pipes in crawlspace
 - gap sealant on gas exhaust
-- proper drainage valves on hot water heater
+- proper drainage valves on hot water heater?
 - gutters left metal intact from previous gutters
   - leaving visible gaps under the shingles that are large enough that small critters could enter the attic. 
   - ~~missing downspouts on gutters~~
   - ~~hole in gutter to right of entrance~~
   - water dripping along wood under upper gutter.
-  - leaking downspout connector entrance
+  - ~~leaking downspout connector entrance~~
 - painting in spots
+  - siding
+  - paint spills on porch, side of house, and upper deck
 - front doors - were measured but not follow up
-- haul off
-  - truss & doors
-  - ladder from painters
-- replace 3 gallons of exterior paint
-  - or 2 since you're leaving two extra trim
+- ~~haul off~~
+  - ~~truss & doors~~
+  - ~~ladder from painters~~
+- replace 3 gallons of exterior paint ๐Ÿ‘ˆ๐Ÿป
 
 **Interior**
 
 - bathroom hardware
-  - shower handrails
-- hvac ductwork 
-- broken shower wand tube
-- bad water pressure
-  - remove water restrictors?
+  - ~~shower handrails~~
+- ~~hvac ductwork~~ 
+- ~~broken shower wand tube~~
+- ~~bad water pressure~~
+  - ~~remove water restrictors?~~
   - check sewer leak?
-- bathtub not properly installed
+  - had failed to clean out heads on faucets.
+- bathtub not properly installed ๐Ÿ‘ˆ๐Ÿป
   - slides around
     - no blocking as specified in manual
   - no additional 2x12s as specified in manual
-  - no backsplash or water proofing on the wall of bathtub
+  - no backsplash or water proofing on the wall of bathtub ๐Ÿ‘ˆ๐Ÿป
   - white caulk on bathtub filler
 - sliding door not caulked
   - sliding poor trim paint/stain
-- ceiling fan
+- ~~ceiling fan~~
 - paint on tile floor
-- no backing support for grab bars behind tile
-  - broken grab bar install
+- ~~no backing support for grab bars behind tile~~
+  - ~~broken grab bar install~~
 - damaged bi-fold doors
   - broken hardware on bifold doors
-  - split wood on the base of doors
+  - split wood on the base of closet doors
 - door hardware for bedroom
 - cracked floor trim from carpet puller
-- closet shelves needs to be split for attic
-  - need to replace closet shelves
-  - need latch on attic door
-- missing baseboards and crown molding
-- carpet doesn't meet baseboards
-  - carpet transition to tile
-  - feel tacks on bare feet
+- ~~closet shelves needs to be split for attic~~
+  - didn't closet shelves
+- ~~carpet doesn't meet baseboards~~
+  - carpet transition to tile ๐Ÿ‘ˆ๐Ÿป
+  - ~~feel tacks on bare feet~~
 - dressing room 
   - drawers/hardware
   - stained seat top
-  - lighting
-- electrical
-  - dimming led cans
-  - dressing room light/switch
-  - bathroom upside down
-  - stairway light switch
-- lots of bad drywall work
+  - lighting? extra switch? ๐Ÿ‘ˆ๐Ÿป
+  - ~~bathroom switches upside down~~
+  - ~~stairway light switch~~
+- lots of questionable drywall/paint work ๐Ÿ‘ˆ๐Ÿป
   - crooked wall in bedroom corner
   - tape marks in ceiling
   - wavy at bed entrance - too many repair pieces
-- downstairs ceiling repair from two separate leaks and jackhammer cracking
-- downstairs bathroom paint
+  - splotchy above bed
+  - spots on bathroom ceiling
+- downstairs ceiling repair from two separate leaks and jackhammer cracking ๐Ÿ‘ˆ๐Ÿป
+- downstairs bathroom paint ๐Ÿ‘ˆ๐Ÿป
 - stairwell trim paint baseboards
-- carpet to tile transition
+
 
 **Minor**
 - window treatments 
   - tub / vertical blinds
   - remove curtain rod
-- tv mount
 
 
 ## Management
@@ -96,11 +104,11 @@ We've had some hiccups along the way, so I just wanted to start list of issues w
 - Timeliness 
   - slow pace - some contractors will work for just a couple of hours a day for a week.
   - took **over a year** to complete the project or **9 months** if you account for the truss manufacturing delay
-- very little inspection of work 
-- General contractor has only been by the site once to check up on work
-  - after the trusses were installed
+- very little inspection of work - **NO** final inspection
+- General contractor has only been by the site twice to check up on work
+  - after the trusses were installed and after the the paint
 - Assistant to GC not on site often
-  - once was after a leak
+  - once on an emergency call after a leak
 - Not much supervision of subs
 - Communication lackluster
   - Inconsistent notice of subcontractors arriving onsite
@@ -117,6 +125,7 @@ We've had some hiccups along the way, so I just wanted to start list of issues w
 - had to drive over to GA to confirm quartz because couldn't get what was promised
 - didn't fix cut drywall in downstairs bathroom for three months
   - left it open and we taped the piece back into it
+  - still not painted
 - contractors on site past normal working hours
 - contractor fishing in pond putting fish in bucket
 
@@ -125,7 +134,7 @@ We've had some hiccups along the way, so I just wanted to start list of issues w
 - studio left without hardware for three months
 - leaking seal on pipe that ran into the wall and stained the ceiling on the floor below in both the den and downstairs bathroom
 - hot water install mixed with cold water
-  - we didn't have cold water for a couple days
+  - we didn't have cold water for a couple of days
 - covered existing electrical outlets
 - didn't seal off area of drywall sanding
   - no ventilation or air treatment
@@ -167,8 +176,8 @@ We've had some hiccups along the way, so I just wanted to start list of issues w
 
 ## Billing
 
-- quotes and invoicing incomplete
-  - requested payment before work was completed
-  - no discussion of invoicing changes
-
-
+- quotes and invoicing inconsistent. 
+- Showed up on site requesting payment before work was completed or inspected
+- No discussion of invoicing changes
+- Invoicing duplicate errors
+- aggressive labor charges